T2.to add 110 megawatts by end of June
The Takoradi 2 (T2) Power Plant is expected to add 110 megawatts (MW) of power to the country's installed capacity from the end of June this year.
President John Dramani Mahama last Thursday inspected work on the new steam turbine under construction at the Aboadze Enclave where he expressed satisfaction with the rate of work.
About 95 per cent of work had been completed.
President Mahama, who was on a two-day working visit to the Western Region, was eager to permanently end the power crisis in the county, and the coming on board of the 110 MW of power in the course of the year would help in solving the energy problem.
Increased capacity
The $30 million project, which started in 2013, will increase the plant's capacity from 220 MW to 330 MW from its combined cycle.
Owned by Takoradi International Company (TICO), the T2 Plant is a joint venture between the Abu Dhabi National Energy Company PJSC (TAQA), which owns 90 per cent shares, and the Volta River Authority, which owns 10 per cent. It is the first Independent Power Project (IPP) in Ghana.
Financing was provided by the International Finance Corporation (IFC) and a consortium of international development finance institutions, including the African Development Bank (AfDB), Deutsche Investitions-und Entwicklungsgesellschaft, OPEC Fund for International Development and the Canada Climate Change Programme.
Company has learnt lessons
Nana Osafo Agyei Kantanka, Managing Director of the TICO, told the President that the company, which was delivering 95 per cent output, fell into difficulties last year.
"But we have learnt our lessons," he said, adding that the company was repositioning itself to face the future with renewed hope.
Gas available
In his remarks, President Mahama said gas was now available in the Aboadze Enclave from Ghana Gas.
He expressed the hope that when all the maintenance work at TICO was completed, there would be enough gas to fuel them so that there would be an increase in supply to keep up with the fast-growing demand for electricity.
President Mahama also inspected the site for the systems to be installed for the 250MW Ameri-Energy/ APR emergency power badge.