Speed up Tema Roundabout to Dawhenya road works - Minister urges contractors

By Nana Konadu Agyeman 4 min read
Governs Agbodza (middle), Minister of Roads and Highways, expressing his dissatisfaction to Oliver Acquah (2nd from right), CEO of First Sky Construction Limited, over the slow pace of work on the Tema Roundabout-Aflao road

The Minister of Roads and Highways, Governs Kwame Agbodza, has expressed displeasure at the slow pace of rehabilitation works on the 17-kilometre stretch from Tema-Roundabout to Dawhenya on the National Road One (N1).

He said the contractors — First Sky Construction and BHM Construction Limited- had done little work since he last visited the project site four months ago.

Sounding blunt, he questioned why the contractors had engaged only two earth gangs of workers on the 17 km stretch and not had similar gangs at both ends of the road.

“You see, when this road is just about 17km and what we have been complaining about is that right from the beginning I get the impression the contractors do not intend to do the work because I do not see any activity,” he said.

Work on the project, which is currently 23.11 per cent complete, started in September 2020.

The road is a critical part of the Trans-West African Highway designed to connect Ghana with ECOWAS countries, facilitating regional traffic and trade.

Speaking during an inspection tour of the road last Wednesday, Mr Agbodza expressed his disappointment at the low level of activities along the road and tasked the contractors to speed up work to ease difficulties the motoring public were currently enduring.

“We see one gang doing a small culvert somewhere on diversion, but diversion allows you to do actual work,” the minister said.

The inspection was to allow the Roads and Highways Minister and his team the opportunity to assess the progress of major road projects under the government's Big Push programme in the Greater Accra Region.

Improvement

Mr Agbodza said public sentiments about the Tema-Aflao road were that there had been some improvement in traffic flow along the stretch.

He said since the contractors carried out some rotary and diversion works, there had been some traffic improvement.

He, however, questioned why, moving from the Tema Motorway Interchange, there were no construction activities along the stretch.

The minister, therefore, urged the contractors to spread construction works along the stretch and stop focusing on earthworks on only a particular portion.

“Today, motorists get stuck because they use only the existing lane,” he said, urging the contractors to add the service lanes right from the Motorway Interchange to open up the traffic road.

He recalled how he and his team got stuck in traffic at TT Roundabout while driving to visit the project site.

Reduced traffic

Responding to the minister's concerns, the Chief Executive Officer (CEO) of First Sky Construction, Oliver Acquah, said the firm had been able to resolve the traffic congestion issue along the stretch to allow the flow of traffic.

He said at Savannah, a point along the road, the company had created a rotary to allow free movement of traffic, while at Prampram junction both contractors had agreed to create two lanes to allow the traffic to be diverted through the Prampram township.

“So, technically, the traffic management has improved considerably,” Mr Acquah said.

Slow progress

The CEO, however, agreed that the general construction work along the 17km had been “slow”.

He said the subcontractor was working upstream but “we think they should be able to do better”.

The CEO added that the original work programme had divided the project into three sections.